How we run projects

Every customer engagement at Northwind follows the same lifecycle so that customers get a consistent experience and so staff can move between projects easily. The VP Delivery, Frank Delgado, owns this framework.

Lifecycle

Phase Purpose Key outputs
1. Initiate Agree scope, team and governance Signed SOW, kick-off plan
2. Plan Detailed plan, risks, communications Project plan, RAID log
3. Deliver Build and test in iterations Increments, demos, release notes
4. Accept Customer reviews deliverables Acceptance record
5. Close Handover and lessons learned Closure report, lessons learned

Roles

  • Account owner: Owns the relationship (usually from Sales). See the customer pages.
  • Delivery manager: Accountable for the programme, staffing, margin and quality (for example Maya Torres).
  • Project manager: Runs the plan day to day (for example Henry Brandt).
  • Solution architect: Owns technical design (for example Isha Patel).
  • Customer sponsor: The customer's decision maker.

Kick-off checklist

  1. Confirm the SOW is signed and approved, see SOW process.
  2. Create the project record and the project folder in the document library.
  3. Hold an internal kick-off, then a customer kick-off.
  4. Agree the communication plan, including weekly status reports.
  5. Agree the definition of done and acceptance process, see Deliverable acceptance.
  6. Set up access for the team via Request access.

Governance rhythm

Meeting Frequency Attendees
Stand-up Daily Project team
Status report Weekly Project manager to customer and delivery manager
Steering committee Monthly Customer sponsor, account owner, delivery manager
Retrospective Every sprint Project team
Internal delivery review Monthly VP Delivery, delivery managers

Managing risk

Keep a RAID log (risks, assumptions, issues, dependencies). Risks with high impact and high probability go in the weekly status report. Problems that cannot be resolved by the project team follow Customer escalation.

Changes in scope

Any change to scope, fee or schedule goes through Handling change requests. Never agree scope changes verbally.

Closing a project

  1. Obtain final acceptance.
  2. Hand over documentation and access.
  3. Reconcile invoices. Invoice numbers use the form INV-2026-NNNN.
  4. Run a lessons-learned session and file the notes in the Projects folder.
  5. Release the team.

See Estimation and Release process for the technical side of delivery.

Owner: Frank Delgado - Last updated: 2026-03-03